EMI Global School Renovation Project

EMI Global School Renovation Project

Estimated Financial Requirements (Renovation-Focused)


Project Overview

The EMI Global School Renovation Project is a targeted, impact-driven initiative aimed at revitalizing existing schools in underprivileged rural and semi-urban communities. Rather than constructing new buildings, this phase of the project focuses on renovation, painting, basic repairs, and the provision of essential learning equipment to create a safe, dignified, and inspiring learning environment for students and teachers.

This renovation-centered approach allows EMI Worldwide and its partners to deliver immediate educational impact with modest financial input, while laying a strong foundation for future expansion and development phases.


Project Objectives

  • Improve the physical condition of existing school buildings
  • Create a clean, safe, and student-friendly learning environment
  • Provide basic furniture and essential learning equipment
  • Restore dignity to public and community schools in underserved areas
  • Support improved learning outcomes through better infrastructure

Scope of Renovation (Per School)

The renovation project typically covers:

  • Repainting of classrooms and external walls
  • Minor structural repairs (walls, floors, doors, windows)
  • Roof patching and basic weatherproofing (where required)
  • Replacement or repair of classroom furniture
  • Provision of basic teaching and learning equipment
  • Light electrical repairs (lighting, fans, switches)

Estimated Budget Summary

Total Estimated Budget (Per School):
USD 8,500 – USD 10,500
(Average target budget: USD 10,000)


Detailed Budget Breakdown

1. Building Repairs & Renovation

ItemEstimated Cost (USD)
Minor structural repairs (walls, floors, plastering)1,800 – 2,500
Door and window repairs/replacement700 – 1,200
Roof patching & weatherproofing800 – 1,500
Subtotal3,300 – 5,200

2. Painting & Aesthetic Improvement

ItemEstimated Cost (USD)
Interior classroom painting900 – 1,300
Exterior painting & branding600 – 1,000
Labour & finishing400 – 700
Subtotal1,900 – 3,000

3. Furniture & Basic Equipment

ItemEstimated Cost (USD)
Student desks & benches (repair or replacement)1,200 – 1,800
Teacher desk & chair300 – 500
Whiteboards / chalkboards250 – 400
Storage shelves & cabinets250 – 400
Subtotal2,000 – 3,100

4. Electrical & Utilities (Light Works)

ItemEstimated Cost (USD)
Lighting fixtures & bulbs300 – 500
Ceiling or standing fans300 – 600
Wiring repairs & switches250 – 450
Subtotal850 – 1,550

5. Project Coordination & Contingency

ItemEstimated Cost (USD)
Local project supervision & coordination400 – 700
Transportation & logistics300 – 600
Contingency (5–8%)300 – 600
Subtotal1,000 – 1,900

Grand Total Estimate

DescriptionAmount (USD)
Total Renovation Cost (Per School)USD 8,500 – 10,500

Partnership Opportunities

Partners and donors may support the project through:

  • Full sponsorship of a school renovation (USD 10,000)
  • Partial sponsorship (painting, furniture, or repairs)
  • Corporate Social Responsibility (CSR) contributions
  • In-kind donations of paint, furniture, or equipment

All partners receive project documentation, impact updates, and recognition in line with EMI Worldwide’s transparency and accountability standards.


Sustainability & Future Development

This renovation phase represents Phase One of EMI’s broader Global School Development Vision. Once safe and functional learning environments are restored, future phases may include:

  • Digital learning facilities
  • Teacher capacity development
  • Library and resource centers
  • Renewable energy solutions

Implemented by:
English Master Institute (EMI) Worldwide
Redefining Education • Empowering Communities • Unlocking Human Potential